Project status report
Progress, risks and next steps, ready for stakeholders.
Read the opening free, then pay £6.99 once for the rest. No account, no subscription.
An example Clara wrote
The opening of a real status report Clara wrote from sample answers: the Depot 2 fit-out, amber after the racking delivery slipped. The names and stories are invented for this example; yours is written only from your answers.
Project: Depot 2 fit-out Period: Week ending 14 November 2026 Author: Amina Patel Overall status: Amber
Status and why
The project is Amber because the racking delivery slipped by a week. The delay is still inside the contingency, so it has not yet affected the wider plan.
Corrective action: the request for weekend working for the installers, set out under decisions below, is intended to recover the time once the racking is on site.
Clara is writing your status report
This takes about 20 seconds. Please keep this page open.
The start of your status report
The rest of your status report is written and waiting.
The full status report is words. You've read the first .
Unlock it for £6.99. One payment, no account, no subscription.
Secure payment by Stripe. Your status report appears straight after paying.
Project status report: what to include
A project status report tells stakeholders, on one page, whether a project is on track and what they need to do about it. Most use a RAG status. Green means on plan. Amber means some slippage, but the end date and budget are safe. Red means the project is likely to be late or over budget and needs help from beyond the project team.
A useful report has a header with the project name, reporting period, author and overall status, then short sections covering why it has that status, what was achieved this period, what is planned next, risks and issues, the budget position and any decisions or help you need. For Amber or Red, explain the cause and the corrective action, with an owner and date where you have them.
Avoid showing a colour on its own: write the word as well, so the status is clear in print and to readers who cannot tell the colours apart. Avoid burying a request for a decision at the bottom of a long update, and avoid a Green rating when the reasons you give describe slippage. Clara uses the status you choose and adds a one-line key explaining the three colours.
Questions people ask
What does RAG status mean?
Red, Amber, Green. Green is on plan, Amber is some slippage with the end date and budget still safe, and Red means the project is at risk and needs help beyond the project team.
What should a project status report include?
The overall status and why, achievements this period, plans for next period, risks and issues, the budget if relevant, and any decisions or help needed.
How long should a project status report be?
One page is usually enough. Stakeholders want the status, the reasons and what you need from them.
Related
- Presentation outline and speaker notes£6.99Your topic, turned into slides and what to say.
- Meeting minutes from rough notes£6.99Turn rough notes into tidy minutes and actions.
- Pitch deck outline£6.99Slide by slide, with speaker notes.
- Client proposal or quote cover letter£6.99A covering letter that helps your quote win.